Rescheduling Production Dates


  1. Navigate to the SCHEDULE and using the FILTER BY ROUTE option (in the right panel), set a filter for the Crew producing the work.
  2. Switch the SCHEDULE to WEEK view and then see options below for adjusting production dates:

Option 1:

• Place your mouse pointer on the left edge of the appointment(s) box (on the colored vertical

bar) and drag/drop to the new date/time



Option 2:

• Click on the appointment(s) and choose MOVE TO DIFFERENT DATE > navigate to the new

date/time > and then double-click to complete the process.